The Plan Everyone Agreed To
Ravindra Dastikop with ChatGPT
We were taught to agree on a date and work backwards. Now that AI can help with that, what should we learn to do?
Everyone in the meeting agrees to a Friday launch. The AI-drafted plan looks ready to circulate. But testing takes two full workdays after a vendor sends the data file, and the vendor has yet to confirm delivery. The next useful step is a question for the vendor. What can they deliver, and when?
Unlearn this. Treating agreement on a draft plan as confirmation that the date is feasible. Start learning this. Check the dependency with its owner before you commit. Until then, label Friday as a target and say what still needs to be confirmed.
Why this card asks you to check the dependency
The U.S. Government Accountability Office’s schedule guide recommends sequencing activities by their dependencies and checking the critical path. In this exercise, the vendor’s file must arrive before testing can start. Working backwards helps you calculate when you need it. The vendor is the source for whether they can meet that date. GAO Schedule Assessment Guide.
In a high-school mathematics field experiment, students using unrestricted AI did better during practice but performed worse on a later unaided assessment than students who had practised without AI. A tutoring version designed to give hints largely mitigated that downside. This gives Card 003 a reason to test unaided performance and informs the fresh case in Card 004. The study tested maths tutoring. Whether this card improves independent scheduling judgment is a question for a workshop pilot. Bastani et al., PNAS, 2025.
Try it in ten minutes
- Write the question you would send the vendor. Decide how to label the Friday launch in your status update.
- Ask AI which assumption could move the launch and have it ask you one question. Revise your message to distinguish the target date from a confirmed date.
- Try a fresh case unaided. A Monday workshop needs one full workday of printing after venue approval. The printer is closed on weekends. Identify what you need to confirm, who owns the answer, and the latest time approval can arrive. Verify your answer against the printer’s work hours.
Project leaders can use this exercise in a planning workshop. After the independent attempt, compare the questions participants would send and check whether the answers would give them enough evidence to update the schedule.
How will I know I am learning this?
I can name the dependency, ask its owner for evidence, and label the date accurately.